BOREHOLE CABLE WINDER

CLIENT -SISHEN IRON ORE 

PROJECT – PLANNED DEWATERING OF MINNING AREA WITH BORE HOLES UP TO 400 m DEEP. THE ELECTRICAL CABLE USED TO BE UNCOILED AND RECOILED BY HAND WITH A HUGE RISK OF INJURIES TO PERSONNEL. WE WERE TASKED WITH MEGANISING THE PROCESS. OUR SOLUTION WAS A TRAILER THAT CAN COIL AND DECOIL THE CABLE OFF UP TO Ø60 x 400 m LONG. USING A PETROL ENGINE DRIVING A HYDRAULIC PUMP.

OUR DESIGN DRAUGHTSMAN AND MECHANICAL ENGINEER WORKED CLOSELY TO ENSURE WE MEET THE CLIENTS NEEDS AND TO ENSURE THE OPERATION CAN PROSEED SAFELY.

THIS PROJECT CONSIST OF 1.) DESIGN AND CALCULATIONS OF ALL MECHANISMS OF THE TRAILER.

                                         2.) HYDRAULICS FLOW DESIGN  

                                         3.) FULLY  SHOP DETAILED DRAWINGS

                                         4.) PR APPROVED 

 